Enjoyed the long weekend in New York, which was my big goal for this week. I was out Friday and Monday—which also happened to be the first day for Ricky, a new Mozillian, and Josh, an intern.

Being in New York with my family was wonderful, and more than made up for the odious travel. Wandering around Prospect Park on a beautiful Sunday afternoon made me think of Seurat: if only it had been a little more pointillist. The only part of the trip that worked well in both directions, though, was Caltrain. On the way to the airport, I just happened to get on the same car as an old high school friend I hadn’t seen in 4 or 5 years (I went to high school 2200 miles from here). Bizarre.

On to the business part:

Last week

  • Put a lot of time into getting ready for Ricky and Josh.
    • Filing 2.1 and 2.2 bugs.
    • Triaging [good first bug]s.
    • Doing preliminary 2.2 work.
  • Either worked on or reviewed basically all of the non-moderator UI for the discussion forums.
  • Reviewed wiki markup.
  • Started looking at new ways to use the SUMOdev meeting.
    • Need to think more about the meeting, mailing list, and channel.
  • Pushed 2.0/1.5.4 then figured out what went wrong.
    • Reviewed the fix for it.

This week (me)

  • Help Ricky and Josh get unblocked.
    • Get Kitsune and Tikiwiki set up.
    • Work through some code review and then turn them loose.
  • Work with Paul on admin and moderation.
    • Then review it.
  • Find the cause of the colossal memory errors.
  • Start planning a project with Josh.

This week (team)

  • Get everyone unblocked and ready to start contributing.
  • Get everyone to show up on the leaderboard.
 
1 Comment

Posted in Articles

 

Weekly Update for 10/05/2010

11 May

Last week

  • Filed lots of 2.1 bugs.
  • Meet with IT and QA in preparation of 2.0 push. (It didn’t go well, but not for lack of planning.)
  • Engineering plan is roughly complete through the end of the quarter.
  • Came up with a plan for an intern project.
  • Reviews.

This week (me)

  • Get things ready for new people starting Monday.
  • Get Sphinx to index the new discussion forums.
  • Make creating new threads work through the UI.
  • Start filing 2.2 bugs.
  • Update Support/Kitsune.
  • Think about ways to improve communication with the larger, more distributed team.
  • Enjoy my long weekend.

This week (team)

  • Push 1.5.4.
  • Finish 2.1 UI.
  • Start 2.1 admin and access control.
  • Get ready for two new people on Monday.
 
Comments Off

Posted in Articles

 

Weekly Update for 03/05/2010

03 May

Last week

  • Onsite. Valuable, but not in the traditional, bug-fixing sense.
  • Started talking about l10n. Identified some key issues.
  • Got a plan in place for live chat.
  • Got in a half day on Friday before the lack of sleep caught up with me.
  • Got some reviews done.

This week (me)

  • Break 2.1 into manageable chunks and file bugs.
  • Fix some of those bugs (particularly bug 561524).
  • Get everyone on the same page for Thursday, our first Kitsune push!
  • Get at least 40% into an engineering plan for the next 3-4 months.
  • Put together some ideas for an intern project.
  • Review lots.

This week (team)

  • By Thursday, let’s be able to handle all regular (ie: non-moderator) actions on the discussion forums on stage.
  • Push 2.0/1.5.4.
 
Comments Off

Posted in Articles

 

Weekly Update for 27/04/2010

28 Apr

I know it’s a bit late and I missed last week. I’m getting better, though!

Last (2) week(s)

This week (personal)

  • WebDev OnSite. Meetings, learning, getting things done in the afternoons.
  • Get production plan in place.
    • And a contingency plan.
  • Work out a plan for live chat with Sam and Matthew.
  • Communicate with localizers our plan for the quarter.
  • Working remotely on Friday.

This week (team)

  • Start to file and fix 2.1/1.5.5 bugs.
  • Iterate on forum stub.
  • Find a wiki markup parser.
  • Cross Ts and dot is for production push.
  • Load test Kitsune.
  • Action items from the SUMOdev meeting.
 
Comments Off

Posted in Articles

 

Weekly Update for 12/04/2010

13 Apr

Last week:

  • Finished bugs 556810 (string extraction) and 554740 (Sphinx tests) and landed both.
  • Finished up work on bug 550515 (concat and minify CSS/JS) and pulled jingo-minify out of Zamboni.
  • Got Hudson up and running!
  • Wrote lots of documentation. Need to ask people if it’s enough.
  • Updated all templates with two-space indenting (bug 558228).
  • Mostly cleaned up strings for L10n (bug 557574).
  • Patched Sphinx API to stop quietly swallowing failed connections (bug 554778).

This week, team goals:

  • Get Kitsune on Verbatim.
  • Solve bug 554206/554210 (UnicodeDecodeErrors)!
  • Polish.
  • Freeze 2.0 on Friday.
  • Get unit test coverage to 90%. (It’s a bit of a stretch but let’s aim for it.)
  • Start on 1.5.4.

This week, personal goals:

  • Lightning talk for next Monday.
  • Reviews!
  • Finish 1.5.4 work (except reviews).
  • Come up with a deployment plan.
 